Finland has ordered Google to stop preparation work at two planned data centre sites, in Muhos and Kajaani, because the company hadn't finished the required environmental impact assessments.

Image: Google sign. Credit: Quartz via Yahoo News.

Google sign
Google sign

Image: Google sign. Credit: Quartz via Yahoo News.

The Finnish Licensing and Supervision Agency (LVV) told Tuike Finland Oy, Google's project subsidiary, to halt all preparatory work by October 23. The order stays in place until both assessments are complete.

What happened

Before the order, work at the sites included clearing trees, removing topsoil, building access roads and storage areas, digging, and altering drainage ditches. “The measures in question will change the environment and cause impacts, the identification and assessment of which are among the key objectives of the EIA procedure,” said Tommi Muilu, who heads the LVV's environmental department.

Planning, measurements and soil surveys can continue. Google's subsidiary must explain by October 14 whether it will comply. If it doesn't, the regulator says it can enforce the order, including with fines.

The chair of the Finnish Association for Nature Conservation told AFP that “nature sites which should be preserved” had been logged in an area of more than 300 hectares.

Google's response

Google told CNBC it will defer to the regulator. “We understand the concerns and have fallen short of our own high standards in this instance,” a spokesperson said, adding that Google acted in good faith under Finland's Forestry Act and is going ahead with commitments that include replanting 130 hectares at Muhos.

The bigger picture

The halt hits Google's largest investment in Europe: at least €13 billion in AI infrastructure across Finland through 2028, at sites in Hamina, Kajaani, Muhos and Vaala. The plan includes a 22-year deal for up to half the output of the Loviisa nuclear plant, extending its life to 2050.

Finland's cool climate and clean power have made it a magnet for data centres. This is a reminder that the AI building boom is running into local rules, and local patience, around the world.